| We are planning to a 420 sq ft rear addition (1st flr only). This will enlarge existing kitchen and FR and combine them. Relocate 1/2 bath to large front Living room which will be converted to ~15'x13' study/den. Would add pics of architect drawings but can't figure out how???
First flr will expand from ~1100 sq ft to ~1500. We plan to split single HVAC to 2 zones thus adding a new unit to the upstairs through attic. Basically, we will not have much use of the existing 1st flr during the interior renovations (it will impact existing kitchen, FR and LR). Question, we have a 6 yr old (starting 1st grade) and 3 yr old (preschool 3 1/2 days), wife stays home and I work from home. We have had others tell us to only do a major renovation that lasts through summer months so we would have flexibility to get outdoors vs. winter which relegates you to the indoors. We pretty much have to live in the house during the project. We will likely occupy the 2nd floor (bedroom area and 2 full baths). However, we anticipate this becoming very uncomfortable if project persists. Builder could start in Sept. which means project can last through Jan/Feb possibly. Do you think this would be a mistake to do considering it will run into winter? Any advice? I know that no time is a good time but would a March start be best at this point? |
Follow-Up Postings:
|
| In that situation, March makes more sense for the reasons you mentioned plus weather. Framing in winter is much more difficult---meaning the possibilities of more trouble and mistakes. And, rain has a less long lasting impact than snow as a rule. Another point is dust/construction debris. Being able to open windows is a huge plus. And, holiday off time is minimized. |
|
| How tight is your budget? The longer into the future you go, the harder it is for your builder or any of his subs to know what their materials costs will be. And sorry to say but companies come and go. The builder right now can probably get firm pricing to begin in Sept. But not in March. The raw materials market is very volatile, with copper and wood costs, as well as freight surcharges. There is know way of knowing, of course. But you do expose your project to higher cost risk the longer out into the future you push it. |
|
| Thanks. we originally bid the drawings to 4 builders. Down to 2 with extensive references and solid portfolios of home additions, remodels. Both were not phased by the time of year to do the construction. They said its HO preference. I imagine that these guys are interested in making money all year round of course. If we start in September here in the northeast we are told it should be airtight in 3-4 weeks. Meaning by mid to late Oct. The rest of the work is the interior remodel from new floors throughout, kitchen, HVAC, etc. Much of the issue is our tolerance to the indoor commotion for however long it takes. As much as we wish to get it done sooner than later, we know that once we start it's both feet in. No pause or reset buttons. The contractors both acknowledged that it would not be easy once they bang through the house. |
Please Note: Only registered members are able to post messages to this forum. If you are a member, please log in. If you aren't yet a member, join now!
Return to the Remodeling Forum
Instructions
- You must be a registered member and logged in to post messages on our forums.
- Posting is a two-step process. Once you have composed your message, you will be taken to the preview page. You will then have a chance to review the contents and make changes.
- After posting your message, you may need to refresh the forum page in order to see it.
- It is illegal to post copyrighted material without the owner's consent.
- HTML codes are allowed in the message field only.
- No advertising is allowed in any of the forums.
- If you would like to practice posting or uploading photos, please visit our Test forum.
- If you need assistance, please Contact Us and we will be happy to help.