Is there a guideline for how to schedule a remodeling job?

Posted by bobbie46 (My Page) on
Thu, Apr 21, 11 at 8:18

I am acting as my own contractor. I want to figure out in what order I should plan the various parts of my job. Architect then permit, remove vegetation, hire foundation person, order bricks for piers, hire framer, electrician and so forth. If anyone has a suggestion or a book to recommend, I would appreciate their input. Thanks.


Follow-Up Postings:

 o
RE: Is there a guideline for how to schedule a remodeling job?

There are several books about Home Owner General Contracting. Home Time (TV show) did an entire series of shows detailing the process of being your own contractor.

You need to find the subs you want early in the process---during the planning if possible. Be aware some contractors will try and get by with less than agreed on work, simply because a home owner is a one time customer and usually has very l;ittle idea of preferred or proper mateiral and methoids of construction.

A lot of people have attempted being their own GC, and found hiring a reliable one is a much better idea.


Are you adding an addition to your house?

First, contact the local codes office to see if your plan is within codes. A drawing (hand made) of the lot, house footprint, and new addition footprint should suffice for the initialdetrermination. No point in hiring an architedt if the addition is not within codes.

Basic process:

Plans.
Dig check.
Permit.
Excavation/footings/foundation. If any plumbing needs to be installed, the plumbers may need to add lines before the foundation work. Concrete will need several days curing time before framing.
Concrete flooring poured(if needed.
Inspections as required.

Framing: flooring support and sub floor. Walls and roof framing. Roofing can be installed(any vents should be installed in the roof during framing---not added later. Exterior sheathing installed. Windows and doors installed. Any reconfiguration of exterior walls that are now interior walls done in this section.
Inspection.

Electrician does rough in. Any HVAC work done. Plumbing rough in done.
Inspection.

Insulation/drywall installed. Exterior siding/painting done.
Inspection if required.

Painting/paneling/interior wall/ceiling treatments.

Finish electrical and trim carpentry.
Baseboard installation depends on type of flooring. If flooring will be wood/tile, installing baseboard is usually done after the flooring. If carpet, the baseboard can be installed before the carpet.


 o
RE: Is there a guideline for how to schedule a remodeling job?

Thanks so much for the suggestions. I appreciate them very much.


 o
RE: Is there a guideline for how to schedule a remodeling job?

You are quite welcome. I hope they help.


 o Post a Follow-Up

Please Note: Only registered members are able to post messages to this forum.

    If you are a member, please log in.

    If you aren't yet a member, join now!


Return to the Remodeling Forum

Information about Posting

  • You must be logged in to post a message. Once you are logged in, a posting window will appear at the bottom of the messages. If you are not a member, please register for an account.
  • Posting is a two-step process. Once you have composed your message, you will be taken to the preview page. You will then have a chance to review your post, make changes and upload photos.
  • After posting your message, you may need to refresh the forum page in order to see it.
  • Before posting copyrighted material, please read about Copyright and Fair Use.
  • We have a strict no-advertising policy!
  • If you would like to practice posting or uploading photos, please visit our Test forum.
  • If you need assistance, please Contact Us and we will be happy to help.


Learn more about in-text links on this page here