We a so excited about our new pool!

Pool Size: 18x20x40
Depth: 3.6 to 8
Perimeter: 110
Area: 720
Pump: 3 HP variable
Tanning Shelf
Decking: 850 sf
Stamped Concrete
Pebble Tec: Tahoe Blue
2 Led Lights
Infloor Cleaning System
Waterfall/Slide/Jump Platform/Rope Swing

Day One

They mapped out the pool!

Comments (53)

  • Cherrytx
    Original Author
    10 years ago

    I am amazed at how fast they do this

  • Cherrytx
    Original Author
    10 years ago

    Almost finished

  • Cherrytx
    Original Author
    10 years ago

    They started at 7:30 this morning and finished around 1pm. Now we wait for 2 days before the plumbing for the infloor cleaning system gets done. I feel like this is going to be a hurry up and wait process LOL

  • lindsgd
    10 years ago

    The biggest wait will be for the gunite to cure.

  • gammiesquiltes
    10 years ago

    It is so much fun watching the build. We had neighbors coming over to sit on the back porch to watch! Very interesting!

  • Cherrytx
    Original Author
    10 years ago

    Day 14
    Gunite

  • Cherrytx
    Original Author
    10 years ago

    Stairs and bench

  • Carnut12
    10 years ago

    That is coming out Great!!!!!!

    Congrats!!

  • Cherrytx
    Original Author
    10 years ago

    Coping and Tile was started today.

  • Cherrytx
    Original Author
    10 years ago

    Tile

  • Cherrytx
    Original Author
    10 years ago

    Coping/Oklahoma Flagstone

  • Cherrytx
    Original Author
    10 years ago

    Forming the waterfall, slide, jump platform.

  • Stefv1
    10 years ago

    Can't wait to see more pictures.

  • Cherrytx
    Original Author
    10 years ago

    Tree will have a rope swing!

  • twingle
    10 years ago

    Fabulous pool! Could you give those of us in planning stage an idea of cost/budget??

  • Cherrytx
    Original Author
    10 years ago

    The pool itself, including pump, lights, decking, pebble tec, tile etc was roughly $47,500. We added the infloor cleaning system which was a little over $5,000. The boulder waterfall/slide we designed is close to $21,000 and the concrete tree for the swing was $12,000.

  • Chris
    10 years ago

    Can't wait to see the slide! How big is it?
    We've signed and are waiting on HOA right now (we are also putting in a waterfall/slide but I'm guessing it will be a lot smaller than yours (Offhand I think it's costing us about $12k)

    Coming along really nicely so far, can't wait to see the finished pool!

  • Cherrytx
    Original Author
    10 years ago

    Havent been on for awhile. They poured and started stamping the waterfall a couple of weeks ago.

  • Cherrytx
    Original Author
    10 years ago

    Some of the rocks that have been stamped.

  • Cherrytx
    Original Author
    10 years ago

    Decking was formed Wednesday.

  • Cherrytx
    Original Author
    10 years ago

    Starting to pour the decking.

  • Cherrytx
    Original Author
    10 years ago

    Decking has been poured and stamped.

  • Cherrytx
    Original Author
    10 years ago

    Still not finished,mother will come back in 5 days to cut stone pattern, stain, and grout

  • Cherrytx
    Original Author
    10 years ago

    Not *mother on previous post LOL
    They are working on the tree and waterfall today. I will take pics of the waterfall later today. They have finished stamping it and have welded the branches to the tree and are putting gunite on it today as long as the rain holds off, fingers crossed.

  • Cherrytx
    Original Author
    10 years ago

    So they have finished the waterfall and tree today. All that's left is the painting and sealing.

  • Cherrytx
    Original Author
    10 years ago

    I love all of the detail they did with the tree!

  • Cherrytx
    Original Author
    10 years ago

    A wider view

  • Cherrytx
    Original Author
    10 years ago

    More details!

  • Chris
    10 years ago

    Looks great! Can't wait to see the finished pool (I'm sure you can't either!).

  • gaylek
    10 years ago

    Awesome! Looking forward to next update also!

  • rmw_
    10 years ago

    That is one expensive tree, but I LOVE it.

    Totally cool idea and they did a wonderful job on it.

    Keep the build details coming!

  • Cherrytx
    Original Author
    10 years ago

    Pebble Tec was done today. Tahoe Blue is the color we chose. Acid wash wash tomorrow then we can start adding water. 3 of the coping stones need to be replaced and the deck still is not finished but we are at least going to get to swim while we wait :)

  • GabrielBer
    10 years ago

    Dear Folks:

    First of all congratulations on your pool.

    We have built a concrete pool, which was casted (walls and floor) all together at the same time.

    In the beginning the contractor was supposed to place an inner PVC liner but since we didn't like this solution he suggested we waterproof the inner part (no the outside which is already covered with clean sand) and cover it either with marbelite or ceramics.
    Do you have any idea of the best material for waterproofing (if needed?) and for the inner cover? Many thanks for your attention.
    Gabriel

  • Chris
    10 years ago

    Any pics with water yet?! :)
    (Living through your build thread at the moment since my dig doesn't start until Saturday!)

  • Cherrytx
    Original Author
    10 years ago

    As a matter of fact I do! LOL we are having to fill it fairly slow because we have a well, no city water :/ This PCM is after 24 hours

  • Cherrytx
    Original Author
    10 years ago

    *pic
    24 hours

  • Cherrytx
    Original Author
    10 years ago

    Today
    72 hours
    They finished the decking today and are spreading some dirt and bringing out my chemicals tomorrow.

  • Chris
    10 years ago

    It looks great. The slide and tree look fantastic.
    What have they got left to do? Looks like you're nearly set!

  • Cherrytx
    Original Author
    10 years ago

    Not much! Just the dirt work and waiting for the pool to fill up so we can add chemicals. I am doing the landscaping myself and it will take some time because we just bought the 12 acres behind us so we will be doing some more land clearing this fall/winter. My girls were swimming in it yesterday and we even grabbed a 5 gallon bucket to pour water while they slid down the slide LOL

  • Chris
    10 years ago

    Is it full yet?! :-P

    More pics! Can't wait to see the final product!

  • gaylek
    10 years ago

    Like your pretty pool! The tree is unique. Haven't seen one of those before. Looking forward to pictures of it being used.

  • Cherrytx
    Original Author
    10 years ago

    It is finally full! I have pool school tomorrow. The water is a little cloudy so hoping to get it cleared up. Got the rope today too for the tree. Hoping to put it up soon. Will post picks tomorrow. Also going to start landscaping, landscaping,landscaping, thank goodness for the sale at
    Houston Garden Center. It is all month long and possibly Sept too!

  • Chris
    10 years ago

    Congrats! Does that mean you'll be swimming this weekend?

    We may go back and buy some more plants/palms. The issue for us we need to keep them alive in pots/planters until the pool is done so maybe 5/6 weeks!

  • gaylek
    10 years ago

    Finished pool pictures?

  • gaylek
    10 years ago

    Please share some finished pictures! Thanks

  • PRO
    Windows on Washington Ltd
    10 years ago

    Looks great.

    Loving the artistic flair.

  • jenspence
    10 years ago

    FYI....someone started a new thread wanting to see final pictures of your build! They couldn't locate this one. They were interested in seeing the tree and rope swing at completion. If you are up for it, we would love to see the final product:)!

  • jenspence
    10 years ago

    The thread they started "tree with swing, where are you?" Or something like that;-)

  • james63038
    9 years ago

    I know it's been some time but wondered if you might give your thoughts after a year?