Wed, Feb 1, 12 at 21:04
| I am thinking about renovating an old Anthoney inground pool. I would like to raise the floor of the deep end from the current 9 feet to about 6 feet.
I am not sure if that is possible? The pluming for the main drain is almost certainly broken. I would like to have two new main drains and plumbing installed at the 6' level and just channel the pipes out through the side wall between the 6' and 9' level. How would a builder go about accomplishing this task? Install re-bar and fill with sand and concrete? |
Follow-Up Postings:
|
| Crushed concrete, compacted for the floor base. Punch a hole in the shell for the new drain line. Dowel in new rebar for the floor and shoot it. Scott |
|
| I think Scott means crushed stone/rock. 3/4" crushed rock is easy to handle and provides a good base. Or recyled concrete that has been thru a crusher.. |
|
| The recycled concrete is exactly what is meant. 3/4 gravel is good too, if available. Scott |
Please Note: Only registered members are able to post messages to this forum. If you are a member, please log in. If you aren't yet a member, join now!
Return to the Pools & Spas Forum
Instructions
- You must be a registered member and logged in to post messages on our forums.
- Posting is a two-step process. Once you have composed your message, you will be taken to the preview page. You will then have a chance to review the contents and make changes.
- After posting your message, you may need to refresh the forum page in order to see it.
- It is illegal to post copyrighted material without the owner's consent.
- HTML codes are allowed in the message field only.
- No advertising is allowed in any of the forums.
- If you would like to practice posting or uploading photos, please visit our Test forum.
- If you need assistance, please Contact Us and we will be happy to help.