Sun, Aug 3, 08 at 22:03
| We are almost done with our major remodeling, which included new two car garage. It turns out that the contractor didn't pitch the floor at a slight angle such that the water will flow outside toward the garage door.
The floor should have been pitched as required in the architectural plans and by the Village building code. To fix this condition, the contractor hired a mason. The mason suggested drilling a hole every 6 inches in the existing concrete floor and to use a wire mesh on the floor. This will allow for the new concrete to adhere to the old concrete floor. Have you come across a similar issue regarding the pitch? Does the solution proposed by the contractor make sense? |
Follow-Up Postings:
|
| How thick is the new concrete going to be? |
Please Note: Only registered members are able to post messages to this forum. If you are a member, please log in. If you aren't yet a member, join now!
Return to the Garages/Workshops Forum
Instructions
- You must be a registered member and logged in to post messages on our forums.
- Posting is a two-step process. Once you have composed your message, you will be taken to the preview page. You will then have a chance to review the contents and make changes.
- After posting your message, you may need to refresh the forum page in order to see it.
- It is illegal to post copyrighted material without the owner's consent.
- HTML codes are allowed in the message field only.
- No advertising is allowed in any of the forums.
- If you would like to practice posting or uploading photos, please visit our Test forum.
- If you need assistance, please Contact Us and we will be happy to help.