Material for base (leveling) of cultured marble shower

Posted by helluvaengineer (My Page) on
Thu, Mar 27, 14 at 11:47

Our existing tile shower stall in the upstairs Master bathroom was leaking and we are finally replacing it. We decided to use cultured marble for reason of ease of maintenance. There was considerable rot after the demo, so the contractor fixed the subfloor and put some additional layers of ply on top.

The cultured marble shower pan sits right up against the studs on the exterior wall, and there is apparently an almost � inch drop between this edge and the unsupported opposite edge. This may be attributable to the age of the home (25 years), but at any rate it�s a real problem since the pan needs to sit flat.

The cultured marble installer (different company) put some shims on the floor to level the pan, then slathered drywall mud under the pan to support it. When I saw what they did I called the owner and said that I was not comfortable with drywall mud as a load-bearing base for the pan. He told me that they have never had a problem with it, and we agreed that they would pull the pan and remove the existing mud, but now I am on the hook for leveling the floor.

My hope was to simply use some self-leveling compound since the area is outlined with 2x4s and the compound should settle nicely within that area. However, I called one company to ask them about the use of their self-leveling products for that application and they said that was not the proper solution. They instead recommended making a base using Sand/Topping mix.

My concern is that everyone I talk to seems to only be familiar with tile shower installations. While I understand that the Sand/Topping mix would be correct for a tile base (with extra sand mixed apparently), is it the best way to build a flat surface for my already waterproof cultured marble base? I want to do the right thing but I am very doubtful that I can trowel something exactly level.


Follow-Up Postings:

 o
RE: Material for base (leveling) of cultured marble shower

It seems like the problem starts at the subfloor. The contractor who fixed the subfloor should have done it in a way so that the subfloor wasn't an inch lower on one side.


 o Post a Follow-Up

Please Note: Only registered members are able to post messages to this forum.

    If you are a member, please log in.

    If you aren't yet a member, join now!


Return to the Bathrooms Forum

Information about Posting

  • You must be logged in to post a message. Once you are logged in, a posting window will appear at the bottom of the messages. If you are not a member, please register for an account.
  • Posting is a two-step process. Once you have composed your message, you will be taken to the preview page. You will then have a chance to review your post, make changes and upload photos.
  • After posting your message, you may need to refresh the forum page in order to see it.
  • Before posting copyrighted material, please read about Copyright and Fair Use.
  • We have a strict no-advertising policy!
  • If you would like to practice posting or uploading photos, please visit our Test forum.
  • If you need assistance, please Contact Us and we will be happy to help.


Learn more about in-text links on this page here