framing section of wall under ac duct work...

Posted by andrelaplume2 (My Page) on
Tue, Aug 18, 09 at 17:42

I have a section of wall that is partially under some duct work. I want to put 1" XPS to the wall then frame in front of that. I can of course secure my pt stud to the concrete floor but can not attach my top stud to any ceiling joists above since the duct work is there.

My thought was to build the section of wall, raise it in place and secure the base plate to the concrete floor. The top plate would not secure to anything so in every other bay I would take a stud and attach it flat against the wall (tapcon thru the face of the stud, thru the XPS into the concrete)and then tie the wall stud into it's side. Does this seam reasonable, code complainat etc.?


Follow-Up Postings:

 o
RE: framing section of wall under ac duct work...

That's what I would do.


 o Post a Follow-Up

Please Note: Only registered members are able to post messages to this forum.

    If you are a member, please log in.

    If you aren't yet a member, join now!


Return to the Basements Forum

Instructions

  • You must be a registered member and logged in to post messages on our forums.
  • Posting is a two-step process. Once you have composed your message, you will be taken to the preview page. You will then have a chance to review the contents and make changes.
  • After posting your message, you may need to refresh the forum page in order to see it.
  • It is illegal to post copyrighted material without the owner's consent.
  • HTML codes are allowed in the message field only.
  • No advertising is allowed in any of the forums.
  • If you would like to practice posting or uploading photos, please visit our Test forum.
  • If you need assistance, please Contact Us and we will be happy to help.



 
Click here to learn more about in-text links on this page.