contractor disorganized, help!

graciesmom284September 13, 2007

hi just wondering if this is typical of contractors. the GC actually. we signed a "contract" spelling out the general work to be done, a room addition and a full bath. it was not however itemized line by line. after several issues regarding the GC not being organized enough to keep the project going smoothly (things not being ordered on time, having the men install the wrong color vinyl trim on the siding, having walls closed up before plumbing was finished , among manyy other things etc...) now he tells us the wood floor he was to install (with us originally just providing the materials and he installs the floor) we must also pay for the installation....as well as the installation of the tile for the bathroom) we think at this point he is "over" the budget in his mind and not making the profit he originally planned on. because of his disorganization his men have had to come back several times to fix all the errors. we think he is just using this to get more money out of us. what do you think? we are willing to split the difference with him at this point to be fair, any advice? this is our first project of this sort. obviously you live and learn...

Thank you for reporting this comment. Undo
Jon1270

Of course you have to pay for flooring installation one way or the other. Directly or indirectly, you pay for everything. The question has to be: was that installation included in the original bid? So, what does the contract say about it?

    Bookmark   September 14, 2007 at 7:33AM
Thank you for reporting this comment. Undo
ron6519

It sounds like both of you are disorganized and lack an attention to detail His omissions could have been deliberate, but you should have been more diligent in oversight. You should of had every item listed on the contract before you signed it. At this point, you are going to have a discussion over every item not mentioned and specified.
This naivete' might be a costly lesson.
Ron

    Bookmark   September 15, 2007 at 11:59AM
Thank you for reporting this comment. Undo
premier

I agree with Ron.

    Bookmark   September 15, 2007 at 10:36PM
Thank you for reporting this comment. Undo
lafdr

I am sorry for your stressful experience. There are a lot of similarities to mine. It is has been very stressful to me to have big holes cut in finished and even painted drywall to fix electrical work that should have been done before the walls were closed up. I disagree with the above posters that you should have known what details were needed in a contract, or should have caught the contractor's mistakes. The contractor is supposed to be the experienced expert who knows what should be in a good contract and the order to do the work in. They should be there at least daily supervising and aware of what is being done. If our general contractor had checked up on his subs more often he could have caught mistakes as they were being made instead of several steps later. Even reading up on the whole topic before hand, there are SO many things I would do differently if I ever did it again. Which I think I won't. I do agree with the poster that you should sit down and go over remaining details/questions and come to an agreement as to what needs to be done and who pays and in writing. So you will at least be at as close an understanding as possible. Email is also a useful papertrail of what is being agreed on. Good luck to a beautiful and finished project as soon as possible.

Thankfully I still owe over 1/3 of the cost. If I was the one owed that much money I would hustle to get the job done in a week, which it could be done in. And if anyone is thinking my delays were due to change orders, that is just not the case. The only change was adding 2 skylights at the framing stage which are long finished. And I did check several references, confirmed valid license, and no prior complaints.

Sign me "6 months into a supposed to be 3 month project, and no one has showed up or called for a week"

or "every day we are half way closer to being done"

    Bookmark   September 19, 2007 at 10:41PM
Thank you for reporting this comment. Undo
scott2006

I hope you didn't give the contractor ALL the money up front.........Your one big leverage is... the money.

Do not pay him one more red cent until he is done and you like it.

If you don't like it when he's done then you can figure out what it's going to cost to fix it and work it from there.

I don't like to do EVERYTHING at once. I like to get one item done then move on to the next.
Oh well good luck.

Scott

    Bookmark   September 30, 2007 at 8:00AM
Thank you for reporting this comment. Undo
dchall_san_antonio

Just out of curiosity, did you have plans drawn up before you selected the contractor? If you don't have a good plan of what the end product is supposed to look like, it is nearly always impossible to chart a path to get there.

    Bookmark   October 3, 2007 at 11:18PM
Sign Up to comment
More Discussions
Shaker style question
What are y'all's opinions on Shaker style cabinetry....should...
janelor
Structural Engineer - What do I need to Know?
I'm planning a kitchen gut/remodel in my three-story,...
Carrie B
Clueless - help me decide on floorplan!
I need help! We are renovating and adding on to a 1600...
essenay
Any reviews of J & K Cabinetry?
We are redoing our kitchen and I came across this type...
Jill_homemaker
Removing brick and install what?
Just for the sake of discussion...if one was to remove...