This may be a basic question but I can't seem to find an answer for us DIYers.

What is the order when remodeling a kitchen? We are doing floors, new cabinets, tile backsplash, countertops, paint, 2 new windows.

I'm most curious on the floor. I was told to do it *after* caninets were installed - no reason to put money towards floors that aren't going to be seen. But yesterday I read somewhere to do cabinet demo, then floor, and then install new cabinets.

Confused!!!

Thank you for reporting this comment. Undo
HandyMac

Demo the cabinets.

Install the new windows and trim(unless the trim interferes with cabinet installation.).

Paint the walls---painting just past where the new cabinets will be. No need to paint where the backsplash will be.

Determine the height on the new flooring. Build up cabinet area with plywood/OSB/whatever to that height.

Install new cabinets.

Install the backsplash.

Install the floor.

    Bookmark   July 14, 2008 at 1:46PM
Thank you for reporting this comment. Undo
sarah428

Thank you!

    Bookmark   July 14, 2008 at 2:42PM
Thank you for reporting this comment. Undo
plants4

Sarah, that's just one answer. There is another answer: install the floor before the cabinets. Part of the answer depends upon what you're using for the flooring. As I understand it, if it's something soft, you would not want the cabinets on top of it. Part of it has to do with being able to pull things like the dishwasher out if it needs to be removed (so it doesn't get wedged in by the floor). There are a variety of reasons. Post your question (or do a search) on the Kitchen forum and you will at least get an answer that it is something to decide, not a set rule as handymac implies.

    Bookmark   July 14, 2008 at 8:19PM
Thank you for reporting this comment. Undo
sarah428

We're putting in cork flooring.

    Bookmark   July 15, 2008 at 9:15AM
Thank you for reporting this comment. Undo
weedyacres

We did floor before cabinets. It has a nicer finished look (no tile edges butting up to the cabinets, and it allows the footprint to be changed later.

If you browse the kitchen forum, you'll see that the topic is often debated. In the end, it's your choice. But do make sure that if you put in the cabinets first, you put plywood under them so they're the same level as the floor.

    Bookmark   July 15, 2008 at 9:29PM
Thank you for reporting this comment. Undo
bill_g_web

I believe for a cork floor, which I assume will be floating, I'd listen to Handymac - put the floor in after the cabs. Check with your floor source/manufacturer for verification. I've heard that the same goes for some floating laminates - don't install anything heavy over the floor - I guess for 2 reasons: The floor will distort under the load and the load will restrict the floor from moving with temp and humidity. If my guess is wrong, maybe someone will correct me.

    Bookmark   July 17, 2008 at 10:59AM
Thank you for reporting this comment. Undo
jams001

If you browse the kitchen forum, you'll see that the topic is often debated. In the end, it's your choice. But do make sure that if you put in the cabinets first, you put plywood under them so they're the same level as the floor.
,There is another answer: install the floor before the cabinets. Part of the answer depends upon what you're using for the flooring.

Here is a link that might be useful: Humidifier Filters

    Bookmark   November 26, 2008 at 4:45AM
Thank you for reporting this comment. Undo
sierraeast

jams001,

Hard to believe these sordid attempts at free advertising by low class idiots. Open up your wallet and advertise legally like classy and succesful business people do.

    Bookmark   November 26, 2008 at 11:21AM
Thank you for reporting this comment. Undo
allison1888

Floors should always be installed under the cabinets. Yes, you waste a little flooring, but it is the professional way to do it.

    Bookmark   November 30, 2008 at 9:55AM
Thank you for reporting this comment. Undo
snoonyb

An interesting segway from the topic,"order of things to be done - kitchen remodeling."

The following is the product of some 30 odd years of remodeling experience.

1) Define the exact area you intend to address.
2) In a kitchen remodel finalize the list of new
appliances, plumbing fixtures and obtain installation
brochures.Will these selections require changes in your
existing elec. and plumbing services.
3) On graph paper, develop a floor plan with the
appliances placed.
4) Select the cabinets, counter and floor covering
material.
NOTE:Keep in mind that "bag-n-box" cabinets, those available from the "big box stores" dimensions are generally divisible by 3" and have a standard toe kick of 4", and that variations are available at an "up-charge."
Custom cabinets do not carry these limitations and you can have a 5" toe kick to compensate for the height of the flooring.
5) Electrical;
Do you have enough counter recep.
Are you planning for under cabinet lighting.
Are you changing your area illumination.
Do you have two appliance circuits.(All counter recp.
must be GFI protected.
Do you have separate circuits for your DW,Disp., Trash
compactor, Microwave and Instant HW?
6) Plumbing;
Are you replacing the sink in-kind, or enlarging?
Are you adding any under sink appliances?
Is your new DW a single appliance or Dish Drawers?
Are you installing Instant H/W or a Tap-master?
Is your Ref. water supply in the right location?
NOTE:Know the product, get estimates, finalize your budget, make the necessary adjustments.
7) Demo the cabinets, order the new, complete all the
framing, elec. and plumbing changes, installation of
windows, patching of damaged wall areas, prime with BIN
or Zinser.
8) If you are installing "bag-n-box" cabinets, anchor 1x3
in the cabinet footprint to adjust the for the
thickness of the new flooring.
Custom should have been ordered with 5" toe kick.
Set 3/4" OSB where all under counter appliances are to
be installed.
Set the rough top and the sink, if it is an under-mount.
Stain and finish custom cabinets.
9) Install the counters, appliances, finish elec. lighting
and plumbing.

  1. Finish painting and wall coverings.
  2. Install flooring.

Why the flooring last?
The only person on the floor after everything that can drug across and or dropped on it, is the homeowner.

    Bookmark   November 30, 2008 at 2:18PM
Thank you for reporting this comment. Undo
sierraeast

We always asked what the floor is going to be before install of the base cabinets and shimmed for height accordingly. That way there are no problems with the dishwasher install as well as any other appliance affected. It was rare to have the flooring installed first no matter the type with the exception of remodels where they kept the existing flooring. The only time now days that flooring should be installed first is with contemporary base cabinets that dont have a toe kick, but are open sitting on legs. Flooring and touch up paint should be one of the last things done wih the last being appliance installs.

    Bookmark   November 30, 2008 at 4:59PM
Thank you for reporting this comment. Undo
jams001

your an idiot sierraeast not me!!!??

    Bookmark   December 1, 2008 at 4:55AM
Thank you for reporting this comment. Undo
sierraeast

Jams001,If you check into the format of the garden web, it states that free advertising by folks who post on the forums is simply not allowed. If recognizing that and following the rules makes me an idiot, so be it. Im sure you are not anymore an idiot than i am and i apologize for the remark, but you should follow the guidelines of the forums in order to keep them intact and not risk losing the advise, experiences that are valued here by many. It's a free forum that could go away by rule breakers. You should respect that!

    Bookmark   December 1, 2008 at 10:47AM
Sign Up to comment
More Discussions
Small bath remodel - problem tub size
I could use some advice. We decided it is high time...
thomis
Potential Contractor wants to have my SS Number ?
Good morning everyone! I'm in the process interviewing...
Marina Yashmanov
Help with exterior remodel!
Help! I want to remodel the exterior of my house. ...
Jeff Holmes
question about getting a bid from contractors
We're getting ready to put an addition on our house...
sparkleblue75
I need help with making a decision to paint golden oak wood or restain
I have a 28 year old view home with dark bronze aluminum...
kimkollie
© 2015 Houzz Inc. Houzz® The new way to design your home™