bathroom flooring question

radtke2tJune 19, 2012

I will be putting in floor heating (electric) in my bathroom and finishing with with ceramic tiles. My question is what order do I put the following materials?

backerboard

self-leveling cement

in-floor heating wires

I have read conflicting opinions on when to apply the self leveling cement. Should it go under the backerboard (on the plywood) or should it just be poured on after the wires are installed on the backerboard?

Thank you for reporting this comment. Undo
weedyacres

The purpose of the SLC is to make an even floor to trowel the thinset onto. So you put the backerboard down, then attach the wires, then pour the SLC over them.

You should use thinset between the plywood subfloor and the backerboard, then screw every 8".

    Bookmark   June 20, 2012 at 7:09PM
Sign Up to comment
More Discussions
Water-based finish over dark stained floors?
Hi all, Folks are about to start flooring work on my...
afrochic2
Filler in travertine marble tiles is coming out causing pitting
We put travertine marble throughout our house. We were...
caribbeancupcake
Tiling on Cement Subfloor or Wood Subfloor?
I live in San Francisco and we are not near any water...
gqchynaboy
Floor sanding/screening question
I just purchased my first home and decided to get the...
berlinswing
Color/species of new wood floor next to original VG Fir?
Our 1918 house was added on to in the 80's and rather...
fjernsyn
People viewed this after searching for:
© 2015 Houzz Inc. Houzz® The new way to design your home™